Budgeting a Project Shipment: The Costs That Arrive After the Freight
Luc Nana, Finance Controller |
A project's logistics budget is usually built around the ocean freight quotation. The costs that break it come later: at the quay, on the road and in the weeks nobody planned for.
When a project team builds its logistics budget, it usually starts with the ocean freight quotation. That is natural: it is the largest single number, it arrives early, and it is easy to compare. The trouble is that it is also the most predictable cost in the whole movement. The costs that push a project over budget are the ones that arrive after the freight.
We see the same pattern on power, mining, telecom and construction projects across Cameroon, Chad and the Central African Republic. The budget is right on the ship and wrong everywhere else.
The costs at origin people forget
Before the cargo is even at sea, a few costs often escape the budget.
- Packing and crating to export standard, including preservation for long storage in a humid climate.
- Survey and inspection before loading, where the buyer, the insurer or the importing country requires it.
- Lashing and securing on a heavy-lift or break-bulk vessel, sometimes charged separately from the freight.
- Changes to the cargo after a route survey shows that a unit must ship in sections.
The costs at the quay
This is where most budgets first go wrong.
- Port handling for heavy and out-of-gauge pieces, which is charged differently from containers and often by weight or volume.
- Cranes and specialist equipment at discharge, where the vessel's gear is not used.
- Terminal storage if the cargo cannot leave immediately, which is common when the road convoy or the customs regime is not ready.
- Demurrage and detention on any containers in the shipment, including flat racks and open tops, which are scarce and expensive to keep.
- Customs duties and taxes, or the guarantees required to suspend them under a project or temporary regime.
- Brokerage, documentation and inspection fees.
The costs on the road
The inland leg is where the budget meets the geography.
- Specialised trailers for heavy and long loads, positioned from wherever they are, often at a cost before they carry anything.
- Road permits for abnormal loads, in every country crossed.
- Escorts, police or gendarmerie where required, and utility crews to lift power and telephone lines.
- Route works: reinforcing a culvert, levelling a ramp, temporarily removing an obstacle.
- Waiting time for trucks and crews when the convoy cannot move: permits not yet issued, a closed road, the rain.
- Transit guarantees for cargo crossing Cameroon to Chad or the Central African Republic.
The costs of time
The largest hidden cost is time, and it shows up in several lines at once.
A heavy unit that waits two weeks at the quay for an exemption accrues storage. The trailer booked for it waits too, or is released and must be rebooked. The installation team on site is paid while it waits for the equipment. The project's commissioning date moves, and with it the revenue or the service the project was meant to deliver.
None of these appear on the freight forwarder's invoice. All of them appear in the project's accounts.
Currency and timing
Project budgets are often set in one currency while costs fall in several: freight in dollars, European handling in euros, local costs in CFA francs. The CFA franc is pegged to the euro, which removes one risk, but freight and some equipment costs move with the dollar. Costs also fall due at different times, some months before the cargo moves and some long after it arrives. A budget should say when each payment is expected, not only how much.
How to build a budget that survives
- Budget the whole route, not the voyage. Ask for a door-to-site estimate that names each cost from factory to final position, including the ones that are only probable.
- Price time explicitly. For each stage, estimate the realistic delay and what a day of it costs in storage, equipment and people.
- Hold a contingency where the risk is. A flat percentage on the whole budget is less useful than a reserve attached to the stages that genuinely vary: the quay, permits and the road in the rains.
- Settle the customs regime before shipment. The cost of a project exemption or temporary admission is small. The cost of waiting for one is not.
- Compare offers on the same scope. A low freight quotation that excludes port handling, lashing or permits is not cheaper than a higher one that includes them.
- Reconcile after each shipment. Compare the budget with the actual costs, stage by stage, and adjust the next estimate.
What a forwarder should give you
A forwarder working on a project should be able to give you a budget broken down by stage, with the assumptions written next to each line, and should tell you plainly which costs are firm and which are estimates. When something changes during the movement, you should hear about the cost before you see it on an invoice.