Out-of-Gauge Into Central Africa: What to Settle Before the Vessel Sails

Joseph Moukoko, Operations Manager |

Cargo that does not fit in a container is planned from the destination backwards. The ship is usually the easy part; the route from the quay to the site is where projects lose weeks.

A generator set, a transformer, a crusher, a bridge beam. Cargo that will not fit in a standard container goes into Central Africa every week, for mines, power stations, roads and humanitarian bases. The shipping of it is a known craft. What surprises clients is how much of the work has to be finished before the cargo leaves the factory.

The rule we work by is simple: plan out-of-gauge cargo from the destination backwards.

Start at the site, not at the port

The first question is not which vessel. It is how the piece will arrive at its final position, and what lies between that position and the sea.

Can the access road on site carry the weight? Is there a crane there, or must one be brought? Is there a bridge on the last stretch, a power line across the road, a bend too tight for the trailer, a town centre that only allows heavy convoys at night? Each of these limits what can be sent, and in how many pieces.

Only once the route from the quay to the site is known can the cargo itself be finalised: whether a unit ships assembled or in sections, how it is crated, where its lifting points are and what its transport dimensions will be.

The route survey

For anything genuinely large, a route survey is not optional. It means someone driving the route with the dimensions of the load in hand, measuring clearances under bridges and cables, checking the condition of bridges and culverts, and noting every point where the convoy will need an escort, a temporary diversion or a lifted cable.

In Cameroon, a survey north from Douala towards Ngaoundéré and beyond, or east towards the border with the Central African Republic, can take time. It is time well spent. A survey that finds a weak bridge before the cargo is built costs a redesign. The same discovery with the cargo on a trailer costs weeks and sometimes a second set of permits.

Choosing the port

Douala and Kribi both handle heavy cargo, but differently.

Douala has the experience, the equipment market and the trucking capacity, and it is closer to the main roads north and east. Its approach channel limits the size and draught of vessel that can come in, which matters for heavy-lift ships.

Kribi offers deep water and a multipurpose terminal with space behind the quay, which suits heavy and bulky units and the larger ships that carry them. The road leg inland from Kribi is longer for most northern and eastern destinations, and that has to be weighed against the easier discharge.

The right choice depends on the vessel, the weight of the heaviest lift and the destination. It must be made at the booking, because the port is written into every document.

Lifting at both ends

Who lifts the cargo off the ship? Some heavy-lift vessels carry their own gear; others rely on shore cranes, which must be available, rated for the weight and booked. Who lifts the cargo onto the trailer at the port, and off it at the site? A lift plan for each of these moments, agreed in advance with the people doing it, prevents most of the incidents we hear about.

Permits and escorts

Abnormal loads on Cameroonian roads need authorisation, and so do loads crossing into Chad or the Central African Republic. Permits specify the route, the times of travel and the escort required. They take time to obtain and are specific to the dimensions declared: a load that grows by a few centimetres after the permit is issued may need a new one.

Budget for the escort, the police or gendarmerie accompaniment where required, the utility crews to lift cables, and the time a convoy will spend stopped while each obstacle is cleared.

Customs for a project

Project cargo is often imported under a special regime: a temporary admission, an exemption linked to an investment agreement, or a project status that changes the duty payable. Each of those has its own documents, and the file must be prepared and approved before the cargo arrives. A heavy unit waiting on a quay for an exemption certificate costs more per day than almost any other cargo.

What to settle before the vessel sails

  • the route survey, and any changes to the cargo it requires;
  • the port, chosen for the vessel and the heaviest lift;
  • lift plans for discharge, loading onto the trailer and placement on site;
  • road permits for every country crossed, with the dimensions as shipped;
  • the customs regime for the project, with its approvals in hand;
  • the convoy schedule, escorts and the window for travel, season included.

Out-of-gauge cargo rewards the client who plans early and punishes the one who improvises. Send us the drawings and the destination as soon as you have them. We will tell you what the route allows, and what has to be decided while it is still cheap to change.